Mid-construction access inspections in NSW: hold points before linings go on

The cheapest time to fix an access defect is before it is covered up. Missing bathroom reinforcement, a door frame set too tight, a shower set-down left out of the slab or a WC pan on the wrong centreline are all easy to correct at the right moment and expensive to fix after the occupation certificate inspection. Sydney Access Consultants offers short hold-point access inspections at set-out, before linings, before tiling and at fit-off, so access items are right before they are hidden. Call (02) 9586 3111.

Why access defects are found too late

A design-stage access report answers one question: does the design comply? An occupation certificate access inspection answers another: was it built that way? Between the two, concealed items often go unchecked. The late finds we see most often are:

Is a hold-point access inspection required in NSW?

No. Mandatory critical stage inspections are carried out by the principal certifier. A hold-point access inspection is not one of them. It is a voluntary check that a builder or developer engages to reduce the risk of access defects at the end of the job. Consent conditions or the certifier may ask for an access consultant's statement before the occupation certificate, and a record of earlier inspections makes that statement much easier to give.

The four hold points we recommend

1. Set-out and slab

Before the pour, we check step-free entries, shower and bathroom set-downs, ramp and landing levels, and the set-out of accessible car spaces. Ramps are assessed against AS 1428.1 clause 10. See wheelchair ramp gradients and accessible car parking.

2. Frame stage, before linings

We check door openings and frame sizes for clear width and circulation space at doors (AS 1428.1 clause 13), reinforcement for grabrails and future fittings, and rough-in heights for switches and outlets. See door circulation space. This is the most valuable visit, because everything it checks is about to disappear behind plasterboard.

3. Sanitary set-out, before tiling

We check the WC pan centreline and its distance from walls, basin position and clearances, and shower falls without a hob, against AS 1428.1 clause 15. See accessible toilet requirements in NSW. If the set-out is already wrong and cannot be moved, a WC pan centreline Performance Solution may be an option, but prevention is far simpler.

4. Fit-off, before handover

We check grabrails, tactile ground surface indicators and luminance contrast, handrails, signage and braille, hearing augmentation and lift controls. The occupation certificate inspection then follows with fewer surprises.

What evidence to keep at each hold point

For SDA work, this evidence feeds directly into as-built SDA certification. Where linings are already on and no photos exist, we verify concealed items such as bathroom wall reinforcement using non-destructive methods where possible, often with detection technology and by removing switch plates and similar fittings.

How this differs from other access services

ServiceWhenWhat it does
DA or CC access reportDesign stageAssesses the drawings against the Premises Standards, the NCC and AS 1428.1
Hold-point access inspectionDuring constructionChecks access items on site before they are concealed or fixed
Occupation certificate access inspectionCompletionChecks the finished building before the occupation certificate
Existing building access auditNo project underwayRecords what an existing building provides and where it falls short

If the design changes on site, the access report may need updating, and where a Deemed-to-Satisfy item cannot be achieved, a Performance Solution should be settled with the certifier before the work is built. On Class 2 jobs, see also design compliance declarations and access.

Building types where hold points pay off most

Booking hold points with Sydney Access Consultants

Book the hold points when the construction programme is set. Visits can be combined where the sequence allows. We are Accredited Access Consultants, ACAA Accredited Member #435, and our practice concentrates on the Sutherland Shire, Cronulla and Hurstville, with work across Sydney. Our free initial consultation is a plan review only. Call (02) 9586 3111 for a fee. For background on DA and CC reports, see DA versus CC access reports.

Frequently asked questions

When should an access consultant inspect during construction?

At the points where access items are about to be concealed or fixed in place: after set-out and before the slab pour, at frame stage before linings, at sanitary set-out before tiling, and at fit-off before handover.

Is a mid-construction access inspection mandatory in NSW?

No. Critical stage inspections are carried out by the principal certifier. A hold-point access inspection is a voluntary check that reduces the risk of access defects being found at the occupation certificate stage.

What does a pre-lining access inspection check?

Door frame sizes for clear opening width, circulation space at doors, reinforcement for grabrails and future fittings in bathrooms, and rough-in heights for switches and outlets, checked against the approved access report and AS 1428.1 before the walls are closed.

How is this different from the occupation certificate access inspection?

The occupation certificate inspection checks the finished building. A hold-point inspection checks the same items earlier, while they can still be corrected without demolition, and leaves photographic evidence of items that will later be hidden.

What if linings are already on?

We verify concealed items such as bathroom wall reinforcement using non-destructive methods where possible, often with detection technology and by removing switch plates and similar fittings.