Multiple Construction Certificates and access reports in NSW

In NSW, a multi-storey building with more than one Construction Certificate under the same consent is locked to the Building Code edition that applied when the CC application for the entrance floor was made, once that CC has issued. With NCC 2025 starting in NSW on 1 May 2027, the entrance-floor CC date decides which access rules the later CCs follow. Confirm the applicable code edition with your certifier. When an access report is prepared, it should match the CC it is written for, and say plainly what it does not cover. Call Sydney Access Consultants on (02) 9586 3111.

Why big NSW projects have several CCs

On a large job you rarely get one Construction Certificate. There is often an early-works or earthworks CC, then a basement, then the podium, the tower and the fit-outs. Separate CCs let construction start before the whole building is documented. Each CC is its own certificate with its own documents, so when an access report is written it has to match that CC. Industry opinion differs on how staged CCs should now be structured; we take no position on that debate here, and your Principal Certifier will tell you how they will issue certificates on your project.

The entrance-floor lock-in, in plain English

What the rule says

Section 19 of the Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021 says a CC is assessed against the Building Code of Australia as in force on the relevant date. Usually that is the date of the CC application. Since 3 February 2023, for a multi-storey building where a CC has been issued under the same consent for work involving the entrance floor, the relevant date for later CCs is the application date of that entrance-floor CC (section 19(1A)). The NSW Government's certifier practice advice summarises the rule, and the amending regulation is on NSW legislation.

What counts as the entrance floor

The entrance floor is the floor containing the principal pedestrian entrance. On a sloping site with entries on two levels, which entrance is "principal" is a judgement for the certifier, so agree it early and in writing.

CCs before the entrance-floor CC

Until the entrance-floor CC has issued, each CC follows its own application date. On our reading, an earthworks CC applied for before 1 May 2027 and a podium CC containing the entrance floor applied for after that date could sit under different editions. Confirm the applicable code edition with your certifier for each certificate.

The CC must name the edition

The Regulation requires each CC to state the edition of the Building Code the certifier considered. Check it on every CC you receive, and make sure the access report for that CC names the same edition.

Modifying a CC

A modified CC keeps the edition that applied to the original application. A modification of the development consent is a different process under a different instrument; see access reports for Section 4.55 modifications.

The Premises Standards and the lock-in

Section 19(1A) locks the Building Code edition for later CCs. The Disability (Access to Premises - Buildings) Standards 2010 are a Commonwealth instrument, and their Access Code has referenced AS 1428.1:2021 since 29 July 2025. There may be a gap between the Building Code edition locked at the entrance-floor CC and the Premises Standards that continue to apply. Raise this early with your certifier and access consultant. This page does not offer a legal conclusion on how the two interact. For the edition question generally, see AS 1428.1 2009 versus 2021.

Three timing scenarios around 1 May 2027

ScenarioEntrance-floor CC applicationLater CCs (tower, fit-out)What the access report says
AApplied for before 1 May 2027 and issuedGenerally stay on the earlier edition (NCC 2022 Amendment 2)Each later report states NCC 2022 Amendment 2 and the AS 1428.1 edition it references
BApplied for on or after 1 May 2027NCC 2025 for the entrance-floor CC and later CCsReports assess the NCC 2025 access provisions; earlier early-works CCs may still sit under NCC 2022
CNot yet lodged; programme flexibleDepends on when the entrance-floor CC is applied forResolve the access design for the edition you will actually be assessed under before you lodge

This is how we read section 19(1A). We are not saying there is, or is not, any other NSW transitional rule for NCC 2025. Your Principal Certifier decides, so confirm the applicable code edition with your certifier for each certificate. What changes for access in NCC 2025 is covered on NCC 2025 access changes in NSW and the timing on NCC 2025 adoption in NSW.

What the access report should say at each CC stage

Early-works, earthworks and basement CCs

These often contain no access work, but a basement can carry accessible car parking, lift lobbies and the path to the lift. We assess basement car parks frequently, typically in child care centres and in mixed-use buildings with Class 7a car parks. Where a basement CC includes parking or lift lobbies, those parts are assessed. Work that belongs to a future CC is never marked compliant.

When a CC contains no access work

We do not issue a scoped statement or a scoped report by default. We look at what the CC contains, assess whether an access report engagement is needed, and advise you on that basis.

The entrance-floor CC

This is the most important access report on the job. It covers the principal entrance, the accessible path from the boundary and parking, lifts and common-area sanitary facilities. It also fixes the edition for later CCs, so resolve the access design before this application goes in.

Tower, residential and fit-out CCs

These cover apartments (including adaptable or Livable Housing features where the consent calls them up), common rooms, rooftop and pool areas, signage and hearing augmentation where required. See apartment access reports, adaptable housing, hearing augmentation and braille and tactile signage.

What every report should name

Each report should name the CC, the drawing set and revision, and the NCC edition, and list what is outside its scope and deferred to a named later CC. That is what certifiers want in an access report.

Performance Solutions that span stages

A Performance Solution approved at one CC can depend on something in a later CC, such as a lift or a path not yet documented. Record the dependency and carry the solution forward to the CC that delivers it. See Performance Solutions and repeated access Performance Solutions.

Regulated designs and declarations on Class 2 jobs

On Class 2 work, regulated designs and design compliance declarations attach to the CC stage. The access package for each CC should line up with the design practitioner's declaration for that CC. See design compliance declarations and access.

At the end: occupation certificates by stage

Partial occupation certificates often follow the CC staging. The final access inspection checks what each CC promised. See occupation certificate access inspections.

How Sydney Access Consultants scopes a multi-CC job

We set one access strategy for the whole building and then, where a report is needed, prepare a report for each CC that matches its documents and edition. Send us the CC programme, the stamped consent and its access conditions, and the drawings for each CC. A DA report is not a CC report; see DA versus CC access reports and access reports for DA, CC and CDC. We are Accredited Access Consultants, ACAA Accredited Member #435. Our free initial consultation is a plan review only. Call (02) 9586 3111 for a fee.

Frequently asked questions

Which NCC edition applies when a NSW building has more than one Construction Certificate?

For a multi-storey building, once a CC has been issued under the same consent for work involving the entrance floor, later CC applications are assessed against the Building Code in force when that entrance-floor CC was applied for. Before then, each CC follows its own application date. This comes from section 19(1A) of the Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021. Confirm the applicable code edition with your Principal Certifier for each certificate.

Does the 1 May 2027 NCC 2025 start date affect our later CCs?

It can. If your entrance-floor CC is applied for before 1 May 2027 and issued, later CCs for the same building generally stay on the earlier edition. If it is applied for on or after 1 May 2027, NCC 2025 applies to it and to later CCs. Each access report should state the edition it assesses against.

Does an earthworks or basement CC need an access report?

Only if the certifier or a consent condition asks for one, or if that CC contains access work. A basement with accessible parking or lift lobbies needs those parts assessed. If the CC contains no access work, we do not automatically issue a scoped statement or report; we assess whether an engagement is needed and advise you.

Does the entrance-floor lock-in also fix the Premises Standards and the AS 1428.1 edition?

The NSW rule locks the Building Code edition for later CCs. The Premises Standards are Commonwealth law, and their Access Code has referenced AS 1428.1:2021 since 29 July 2025. There may be a gap between the two. Discuss it early with your certifier and access consultant.

Who decides which floor is the entrance floor?

The certifier, based on where the principal pedestrian entrance is. Agree it in writing early, especially on sloping sites.

Can one access report cover several CCs?

It is clearer to match each report to one CC, its drawings and its edition. One access strategy can sit above all of them.